| Scaffolding - Fixed (PL13)
Hazards | Risk Rating | | Danger of personnel falling | High | | Danger of falling objects to personnel below | High | | Scaffolding collapsing | Medium | | Vehicles hitting scaffolding | Low | | | | | | |
Planned Methods To Reduce Risks Scaffolds shall be inspected daily before use.
Guards and debris netting will be installed as necessary.
Personal protective equipment will be provided for the staff.
Scaffolds will be inspected regularly to ensure that no unauthorised alterations have been made to the structure.
Only suitably qualified staff will install and dismantle the scaffolding.
The electrical contractor will ensure all the scaffolding complies with current legislation and codes of practice.
Traffic movement will be restricted around the base of the scaffolding.
|