Return to Main Menu


Testing and Commissioning (IM5)


Hazards

Risk Rating

Electrical shocks to site staffHigh
Damage to equipmentMedium
  
  
  


Planned Methods To Reduce Risks

  • If necessary, a permit to work system will be operated.

  • Only competent persons with suitable test equipment shall carry out the testing and commissioning.

  • Planning will include liaison with other contractors and those in control of the premises to ensure that all are aware of the work to be carried out.

  • The electrical contractor shall carry out all testing and commissioning strictly in accordance with the current legislation.